Indian Railways on Friday achieved a major breakthrough in the 6.59-km-long Tunnel-14 of the Rishikesh-Karnaprayag rail project in Uttarakhand’s Rudraprayag district, marking a significant step forward in the construction of the strategically important railway line.
The breakthrough connected two excavated sections of the tunnel — a 4.7-km stretch from Portal-1 at Sumerpur and a 1.79-km section from Portal-2 at Marora.
According to the Ministry of Railways, construction involved several challenging engineering operations, particularly at Portal-1, where a 110-metre stretch of the triple-track tunnel was excavated through loose soil beneath inhabited areas, with only 20-30 metres of soil and rock overhead. Special techniques, including pre-excavation and multi-drifting, were employed to ensure safe construction.
At Portal-2, engineers stabilised the slope using deep micropiles, rock bolts and consolidation grouting. The main tunnel excavation began in March 2024 after ground settlement issues at Marora and matters related to land and house acquisition were resolved.
Around 100 metres of the tunnel at Portal-2 was excavated mechanically, while controlled blasting was carried out during daytime hours near both portals to protect nearby settlements.
The breakthrough is an important milestone for the 125 km long Rishikesh-Karnaprayag rail project, which is expected to improve connectivity to Uttarakhand’s hill districts, facilitate pilgrimage and tourism, and boost regional economic development.